Woburn Forest Center Parcs Balance Tank

  • Sector:Water & Utilities
  • Client:ACWA
  • Location:Woburn, Bedfordshire
  • Value:£485k

As part of upgrades to the waste water treatment system at Woburn Forest Center Parcs, Barhale were contracted by ACWA to construct a new 1200m3 balance tank and undertake associated civils. The increased tank capacity will provide operational and emergency resilience for expanded village facilities, which includes 57 luxury accommodation lodges at the popular holiday site.

Despite challenging conditions, which included cold winter weather, working in an area adjacent to guest accommodation, and modifications to the initial scope that increased the volume of work, the Barhale team finished the work within cost and programme, and in accordance with all technical standards.